On September 24, 2026, the Lexington Planning Commission spent about 10 minutes on the three largest housing proposals in the city's new growth areas and decided none of them. Andover Commons by Anderson Communities on Todds Road, Ball Homes' 560-unit plan, and OK Gentry's 434 apartments off Athens-Boonesboro Road were all postponed at the applicants' request before anyone heard them. The other five rezonings on the docket got the same treatment.
That was more than three years after the Urban County Council voted to expand the Urban Service Boundary. If you're comparing Lexington with Georgetown, Nicholasville or Richmond and assuming a wave of new Fayette County homes is about to land, that hearing is the best guide to the timing. Lexington has the land. What it doesn't have yet are enforceable design rules for that land or a settled answer on who pays for the roads and pipes under it. Until both exist, the expansion areas won't add to the supply you're shopping in.
How three years went by
Here is the timeline from the public record:
- June 1, 2023. The Council voted 10–3 for an expansion of 2,700 to 5,000 acres. It left parcel selection to the Planning Commission and set a Dec. 1, 2024 deadline for a master plan.
- November 2023. The Planning Commission picked about 2,800 acres in five areas on a 6–4 vote.
- Oct. 31, 2024. The Urban Growth Master Plan became part of Imagine Lexington 2045 at a Planning Commission public hearing.
- Jan. 22, 2026. The Council approved the first rezoning inside the new areas 14–0: 73.72 gross acres on Canebrake Drive, owned by former mayor Scotty Baesler.
- Aug. 31, 2026. A zoning text amendment was filed to turn the master plan's advisory language into enforceable standards.
- Sept. 24, 2026. All eight rezonings on the docket were postponed, including every large expansion-area proposal.
When the master plan was being drafted in 2024, the planning consultant called three years to construction aggressive and five years more realistic. Our research found no public record of a building permit, a recorded lot or a construction start in any of the five areas as of early October 2026.
The five areas, and how much of each you can actually build on
On paper, the expansion is big. The Herald-Leader reported in January 2026 that the master plan could hold as many as 24,508 homes, against an estimated backlog of 22,549 units of current demand. But those are capacity and need estimates. Neither one is a count of homes that have been approved or built.
The area-by-area plans published in July 2024 show the first constraint. A large share of every area can't be built on.
| Area | Total acres | Buildable acres | Proposed homes |
|---|---|---|---|
| Winchester Road–Hume Road | 1,097 | 492 | 6,342 |
| North of Athens-Boonesboro Road near I-75 | 641 | 382 | 4,976 |
| Todds Road–Canebrake Drive | 497 | 289 | 3,462 |
| South of Athens-Boonesboro Road near Lexington Sporting Club | 215 | 134 | 1,214 |
| Parkers Mill Road–Man o' War Boulevard | 163 | about 98.5 | 1,335 |
Buildable land runs from about 45% of the total in the Winchester Road–Hume Road area to about 62% south of Athens-Boonesboro. A sinkhole, green space, roads and stream buffers limit the Parkers Mill tract. The north Athens-Boonesboro plan also holds sites for a school and a police or fire station. The area figures in that reporting add up to 2,613 acres, while the plan's stated gross total is 2,833. So the subarea numbers are useful for scale, not as an exact ledger.
The proposed home counts are high for the land because the plan calls for walkable, mixed-use neighborhoods with town centers, a range of housing types, natural drainage buffers and a connected street grid. That design goal is exactly what the current proposals are being held to.
Why the biggest plans keep getting sent back
Before the September hearing, planning staff recommended postponing every case. For the expansion-area proposals, the staff reports listed missing service roads, avenues in the wrong places, cul-de-sacs that were too long, blocks that were too big, no stub streets connecting to neighboring land, and traffic studies that were incomplete or missing. The commission's own Zoning Committee reached the same conclusion on Sept. 3.
That's a specific kind of problem. Long cul-de-sacs and large blocks are standard in suburban subdivisions. The master plan asks builders for something closer to a grid. The applicants' own words at the hearing showed what that means in practice. "It's just going to take us a little bit of time to actually do the development plan work," said the representative speaking for OK Gentry, according to Lexingtonky.news. The Anderson Communities representative said, "We're continuing to make our changes to the plan. We met with the association Tuesday. We want to give everybody a little more time to react."
Andover Commons shows what a proposal built for those standards looks like. The filed concept for the Germond farm at 4200 Todds Road includes 241 detached houses, 195 townhouses, 642 apartments, 74 flats, 26 carriage apartments and 62 senior cottages, plus a 65,141-square-foot town center. Detached houses make up about a fifth of the units. If you're picturing the expansion as a fresh supply of single-family lots, that mix is worth knowing about. It's also still a proposal, not an approval.
Meanwhile, the rules themselves are still being written. Much of the master plan uses "should" language. The text amendment filed Aug. 31 would turn that into enforceable standards, and it has a work session and a hearing on the city's calendar for Oct. 15 and Oct. 22. Builders are revising site plans against a standard that is still taking shape.
The bill under the ground
The second unsettled question is money. A 2024 estimate put the expansion's infrastructure at a minimum of $570 million. That figure doesn't include local roads, stormwater, water lines or new schools. It covers major road and intersection improvements, parks and trails, and public-safety facilities. The same estimate expected more than 90% of the cost to come from developers and less than $53 million from local government. It also projected about $7.8 million a year in added police, fire and other service costs at buildout.
Officials said in fall 2024 that the cost-sharing method hadn't been decided. By November 2025, the Herald-Leader reported that the city was preparing an infrastructure-cost program, and that whatever policy it adopts could change the master plan's 90%-from-developers assumption. For a builder, that number decides whether a lot pencils out. For a buyer, it's part of what any future home there will cost.
The one tract that cleared every vote
Canebrake Drive is the farthest along, and it shows that a rezoning is still a long way from a house. The Baesler property at 200, 201, 250, 251 and 301 Canebrake Drive was rezoned from agricultural to R-4 medium-density residential and I-1 light industrial. The concept described in November 2025 called for 168 apartments in five buildings, 50 detached houses, five duplexes, eight four-plexes and 21 possible industrial buildings. Land-use attorney Nick Nicholson called it "a plan that directly addresses the two biggest reasons why the council pointed to an expansion: for job growth and for housing growth." He also said no developer was lined up at the time. Our research found no later public report naming a developer or a construction start.
Even with zoning approved, the steps between a vote and a closing are still ahead: a developer, a final development plan, infrastructure, permits, and then building.
What that means for the market you're actually shopping
Without expansion-area supply, Lexington buyers in 2026 are working with existing homes and infill, and that market has loosened on its own. Bluegrass Realtors' August 2026 report, published Sept. 23, put the Fayette County median at $362,500, up 3% from August 2025, on 331 sales, down 11%. Across the association's 38-county region, August inventory reached 4,578 homes, the 34th straight month of year-over-year growth, with 3.6 months of supply. New-construction sales hit 124, the highest August total since 2008. Those inventory and new-construction figures are regional, not Fayette-only.
For comparison, the same August 2026 county table shows a $355,000 median in Scott County and $327,000 in Jessamine County. That's today's spread. The expansion areas may eventually affect it, but on the current record they won't do so before buildable lots exist.
The process for future expansions has changed too. In February 2026, the Council voted 14–0 to set up a five-year Preservation and Growth Management review. Any future boundary decision will first take a hard look at infill and vacant land before any new ground is added. So the 2023 areas are the only expansion supply in the pipeline for some time.
The dates that will move this forward
- Oct. 8, 2026: Andover Commons returns to the Planning Commission.
- Oct. 15, 2026: Work session on the implementation text amendment.
- Oct. 22, 2026: Ball Homes' 560-unit plan at 5085 Athens-Boonesboro Road, plus the text amendment hearing.
- Nov. 19, 2026: OK Gentry's 434-unit plan at 5530–5660 Athens-Boonesboro Road.
Any of these can be postponed again, as all eight cases were in September.
FAQ
Is any home in the 2023 expansion areas for sale yet? Our research found no public record of permits, recorded lots or construction starts in any of the five areas as of early October 2026.
Would a rezoning approval this fall mean homes next year? Not necessarily. Canebrake Drive was rezoned in January 2026 and still had no publicly reported developer. After rezoning come final development plans, infrastructure and permits.
Will the expansion bring Lexington prices down? Nothing in the record measures that effect. The 24,508-home capacity figure is a planning ceiling, not a forecast of what will be built.
If you're deciding whether to buy now or wait for new construction off Todds Road or Athens-Boonesboro Road, or you own land near one of these five areas and want to know what it's worth today, Thaddeus Blevins can walk you through the current numbers and the hearing calendar together. Get Your Free Home Valuation to start with what your property is worth in this fall's market.